Tsawwassen Mills Shopping Centre

Project Description: New 1.2 million square foot retail shopping centre located on Tsawwassen First Nation Lands off Highway 17 in South Delta.

Mainland's Role

Primary supplier of aggregate to the project. Mainland supplied over 3.2 million tonnes of aggregate.

Prime Contractor

Ledcor Construction

Timeline

2014-2016

Aggregate Supply

  • River Sand
  • Quarried Stone
  • Densification Stone

Logistics Service

  • Truck delivery – sustained a daily delivery rate in excess of 20,000 tonnes of aggregate per day for weeks at a time
  • Marine delivery
  • Barge loading
  • Installed and operated a truck weigh scale on the project site

Material Handling

  • Removal of surplus material from project site